Kolby’s Korndogs is looking at a new sausage system with an installed cost of $801,000. This cost will be depreciated straight-line to zero over the project’s six-year life, at the end of which the sausage system can be scrapped for $112,000. The sausage system will save the firm $200,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $58,000.
If the tax rate is 35 percent and the discount rate is 7 percent, what is the NPV of this project?