The rustin transportation planning board estimates the cost


Question: The Rustin Transportation Planning Board estimates the cost of upgrading a 4-mile section of 4-lane highway from public use to toll road to be $85 million now. Resurfacing and other maintenance will cost $550,000 every 3 years. Annual revenue is expected to average $18.5 million for the foreseeable future. If i = 8% per year, what is (a) the capitalized cost now, and (b) the equivalent A value of this capitalized cost? Explain the meaning of the A value just calculated.