The results of a time study to perform a quality control


The results of a time study to perform a quality control test are shown in the following table. On the basis of these observations, determine the normal and standard time for the test, assuming a 23% allowance factor.

Task Element

Performance Rating (%)

Observations (minutes)

1

2

3

4

5

1

97

1.5

1.8

2.0

1.7

1.5

2

105

.6

.4

.7

3.7a

.5

3

86

.5

.4

.6

.4

.4

4

90

.6

.8

.7

.6

.7