The purpose of reviewing lessons learned at the end of a phase is all of the following except:
a. Increase effectiveness of the project team going forward.
b. Identify processes that worked well to produce the desired result.
c. Verify that all deliverables have been accepted.
d. Review past issues that may provide information regarding future risks.