1a. The project start-up phase is complete, and your now ready to finalize the operational plan. Below are six steps that are often part of the finalization procedure. Place them in the appropriate order.
- Draw diagrams for each individual WBS element.
- Establish the work breakdown structure and identify the reporting elements and levels.
- Create a coarse (arrow-diagram) network and decide on the WBS.
- Refine the diagram by combining all logic into one plan. Then decide on the work assignments.
- If necessary, try to condense the diagram as much as possible without losing clarity.
- Integrate diagrams at each level until the desired plan is achieved.