The project manager for an organization has identified the following activities and activity times for the installation of a new accounting software system. (Note: time estimates are in weeks)
a. Calculate the expected time and variance for each activity.
b. Draw the network diagram for the project.
c. Solve the network for the critical path, Be sure to list the slack associated for each activity.