The project manager estimates that the value of the work


Problem 2. A project has just completed its 87th item in the project plan. It was scheduled to have spent $300,000 at this point in the plan, but has actually spent only $250,000.

The project manager estimates that the value of the work actually finished is nearly $200,000. What are the spending and schedule variances for the project?

What are the SPI and CPI? What is the Critical Ratio?

a. CV =

b. SV =

c. SPI =

d. CPI =

e. CR =

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The project manager estimates that the value of the work
Reference No:- TGS02716156

Expected delivery within 24 Hours