1. The project cost estimate is allocated to
the various work packages in the project work breakdown structure.
the resources in the project.
the committed costs in the project.
the stakeholders.
2. Calculate the cost variance if the cumulative earned value is $10 and the cumulative actual costs are $20.
$10
-$10
0.5
2.0