The primary control loop of a nuclear power plant includes a time delay due to the need to transport the fluid from the reactor to the measurement point as shown in Figure DP9.11. The transfer function of the controller is
![](https://test.transtutors.com/qimg/28ffd66c-6545-4df2-82c3-6039054414d1.png)
The transfer function of the reactor and time delay is
![](https://test.transtutors.com/qimg/253ff7c4-0965-48d0-8876-932026aa9fbf.png)
where T = 0.4 s and τ = 0.2 s. Using frequency response methods, design the controller so that the overshoot of the system is P.O. ≤ 10%. With this controller in the loop, estimate the percent overshoot and settling time (with a 2% criterion) to a unit step. Determine the actual overshoot and settling time and compare with the estimated values.