In 2013, Tommy's Construction Corp began construction work under a three- year contract. The contract price is $1,600,000. They use the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2013, is as follows:
Balance Sheet
Accounts receivable (from construction progress billings) Construction in progress
|
$ 100,000
|
$ 30,000
|
Less: Billings on construction contract
Cost of uncompleted contracts in excess of billings
|
(94,000)
|
6,000
|
Income Statement
Income (before tax) on the contract recognized in 2013 $ 20,000
Required:
- What was the cost of construction actually incurred in 2013?
- How much cash was collected in 2013 on this contract?
- What was the estimated cost to complete as of the end of 2013?
- What was the estimated percentage of completion used to calculate income in 2013?