The most likely outcomes for a particular project are


The most likely outcomes for a particular project are estimated as follows:

Unit price: $50

Variable cost: $30

Fixed cost: $370,000

Expected sales: 36,000 units per year

However, you recognize that some of these estimates are subject to error.

Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate.

The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreciated straight-line over the project life to a final value of zero.

The firm’s tax rate is 30% and the required rate of return is 14%.

What is project NPV in the best-case scenario, that is, assuming all variables take on the best possible value? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

NPV $

What is project NPV in the worst-case scenario? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

NPV $

Request for Solution File

Ask an Expert for Answer!!
Financial Management: The most likely outcomes for a particular project are
Reference No:- TGS01227969

Expected delivery within 24 Hours