A Company allocates materials handling cost to the company's two products using the below data:
Modular Homes Prefab Barns
Total expected units produced 9,900 16,000
Total expected material moves 1,000 980
Expected direct labor-hr per unit 560 490
The total materials handling cost for the year is expected to be $200,000.
If the materials handling cost is allocated on the basis of direct labor-hours, how much of the total materials handling cost would be allocated to the Prefab Barns?