Understanding MPS:
Part1
The master production schedule is related to MRP and the production plan in that:
I: The MPS drives the production plan
II: The MPS disaggregrates the production plan
III: The MPS is the starting point for MRP
Which combination of statement(s) is true?
a). II only
b). II and III only
c). I and II only
d). I, II, and III
Part2
Typical uses of master schedule activity include which of the following?
I: Driving a material requirements planning system
II: Planning future production
III: Employing rough-cut capacity planning
IV: Establishing the production plan
Which combination of use(s) are correct?
a). I only
b). II and III only
c). I, II, and III only
d). I, II, III, and IV