The product structures for end items A and S are shown in Figure 1. All items have a one-week lead time. Currently there are 20 units of A available, 15 units of S and 90 of C. The standard lot sizes are 50 for A, 35 for S and 100 for C. The master production schedule calls for 20 units of item A and 15 units of item S for each of the next five weeks. An open order for 100 units of item C is scheduled for receipt in week 1. Create the MRP records for items A, S and C.
Note - As i am unable to load the product structure image.
Below are the details of the product structure
End Item A (Leve 0) - Has 2B, 1C, 3D (All these are Level 1)
End item S (Level 0) - Has 2C, 1T, 1U (All these are Level 1)
Please help & provide solution