The manager has assigned an inefficiency factor of 08 to


Problem

A machine cell uses 211 pounds of a certain material each day. Material is transported in vats that hold 20 pounds each. Cycle time for the vats is about two hours. The manager has assigned an inefficiency factor of .08 to the cell. The plant operates on an eight-hour day.

How many vats will be used? (Round up your answer to the next whole number.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The manager has assigned an inefficiency factor of 08 to
Reference No:- TGS02715916

Expected delivery within 24 Hours