The manager finds that there are 100 applications in the system. Based on the last week’s performance, his staff can process 1000 applications in a week (assume one week has 5 days and one day has 8 hours). Suppose it takes 10 minutes to process one application. What is the cycle time, throughput and throughput efficiency?