The lestest start times of activity r s and u at the end of


The duration of activity M, N, P and Q are 37, 34, 41, and 34 days respectively. the duration of activity F, G, H, and K are 34, 37, 22 and 26 days, respectively. the lestest start times of activity R, S, and U at the end of the day of 116,112, and 124, respectively. perform the backwards pass of CPM

1) the latest finish time of activity F is at end of day?

2) the latest finish time of activity G is at end of day?

3) the latest finish time of activity H is at end of day?

4) the latest finish time of activity C is at end of day?

5) the latest finish time of activity D is at end of day?

6) the latest finish time of activity E is at end of day?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The lestest start times of activity r s and u at the end of
Reference No:- TGS02591264

Expected delivery within 24 Hours