The lead time to receive an order from the manufacturer is


A computer products store stocks color graphics monitors, and the daily demand is normally distributed with a mean of 1.6 monitors and a standard deviation of 0.4 monitor. The lead time to receive an order from the manufacturer is 15 days. Determine the reorder point that will achieve a :

a. 98% service level

b. 95% service level

c. 90% service level