The High-Rise Building Company uses 400,000 tons of stone per year. The carrying costs are $100/ton. The cost per order is $500.
a. Calculate the optimal number of orders per year.
b. Calculate the optimal annual order costs.
c. Calculate the total costs of optimal inventory.