The footprint of a proposed office building is overlaid on the existing contours topographic map of a sloping site as shown in the figure. The structural bays which are 65-ft by 65-ft. Determine the amount of excavated material (yd3) to bring the footprint to the sub-grade elevation of 57-ft.