The following table describes the revenue per machine


Pettibone Traverse Lift in Baraga is trying to determine if they should be making some of their machine frames in-house versus buying them from external suppliers. Engineering has determined internal consumption rates of steel and labor to produce each frame plus a setup cost required to create the frame production line. There is a demand 26, 26, 52, 12 respectively for the Cary-Lift, Speed Swing, Extendo and Traverse model frames. Labor cost is $36 per hour with a $18 per hour overhead rate. There are 1,200 hours of labor available during the planning period. Currently steel cost $1.98 per pound. The following table describes the revenue per machine; outsource cost per frame and consumption for each frame if made internally.

 

Cary-Lift

Speed Swing

Extendo

Traverse

Selling price

$36,000

$37,500

$48,000

$51,500

         

Sub 1 cost each

$8,900

$9,200

   

Sub 2 cost each

   

$10,500

$10,900

Steel (lbs)

3600

4400

5000

5400

Labor (hrs)

17

21

22

28

Setup cost

$22,100

$22,100

$36,000

$36,000

Create an Excel model to determine which models Pettibone should setup to make internally and buy to maximize revenue.