PLEASE SHOW WORK SO I KNOW HOW TO DO IT.
The following table contains information regarding jobs that are to be scheduled through one machine:
OPERATIONS TIME
|
JOB
|
PROCESSING TIME(DAYS)
|
DUE DATE
|
A
|
4
|
10
|
B
|
12
|
20
|
C
|
2
|
30
|
D
|
11
|
18
|
E
|
10
|
10
|
a) What is the shortest operating time (SOT) schedule?
b) What is the slack time remaining (STR) schedule?
c) For the schedule A-B-C-D-E, compute average lateness?