The following set of seven jobs is to be processed through


Question -

The following set of seven jobs is to be processed through two work centers at George Heinrich's printing company. The sequence is first printing, then binding. Processing time at each of the work centers is shown in the following table:

Job

Printing

Binding (hours)

T

15

3

U

7

9

V

4

10

W

7

6

X

10

9

Y

4

5

Z

7

8

a) What is the optimal sequence for these jobs to be scheduled?

b) Chart these jobs through the two work centers.

c) What is the total length of time of this optimal solution?

d) What is the idle time in the binding shop, given the optimal solution?

e) How much would the binding machine's idle time be cut by splitting Job Z in half?