The following schedule was prepared by the production


The following schedule was prepared by the production manager of Marymount Metal Shop:

CUTTING                             POLISHING

Job

Start

Finish

Start

Finish

A

0

2

2

5

B

2

6

6

9

C

6

11

11

13

D

11

15

15

20

E

15

17

20

23

F

17

20

23

24

G

20

21

24

28

Determine a schedule that will result in earlier completion of all jobs on this list.