The following represents a project that shouldbe scheduled


The following represents a project that shouldbe scheduled using CPM:

Time (DAYS)

Activity Immediate Predecessors a m b

A - 1 3 5

B - 1 2 3

C A 1 2 3

D A 2 3 4

E B 3 4 11

F C, D 3 4 5

G D, E 1 4 6

H F, G 2 4 5

a. Draw the network

b. What is the critical path?

c. what is the expected project completion time?

d. What is the probability of completing this project within 16 days?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The following represents a project that shouldbe scheduled
Reference No:- TGS01092795

Expected delivery within 24 Hours