The following jobs are waiting to be processed at Jeremy La Montagne's machine center. Today is day 250.
Job
|
Date Job Received
|
Production Days Needed
|
Date Job Due
|
1
|
215
|
30
|
260
|
2
|
220
|
20
|
290
|
3
|
225
|
40
|
300
|
4
|
240
|
50
|
320
|
5
|
250
|
20
|
340
|
Using the critical ratio scheduling rule, in what sequence would the jobs be processed?