The following jobs are waiting to be processed at Jeremy La Montagne's machine center. Today is day 250.

Job

Date Job Received

Production Days Needed

Date Job Due

1

215

30

260

2

220

20

290

3

225

40

300

4

240

50

320

5

250

20

340

Using the critical ratio scheduling rule, in what sequence would the jobs be processed?