The following information concerns progress at day 40 of an Internet marketing project. Determine if the project is in control based on time and cost to date. If not, what is the cost overage or underage?
Activity
|
Duration
|
Budget
|
Actual Cost
|
% Complete
|
1-2
|
10
|
300
|
250
|
100.00
|
2-3
|
8
|
400
|
450
|
100.00
|
2-4
|
12
|
350
|
380
|
100.00
|
4-3
|
0
|
0
|
0
|
|
3-5
|
18
|
405
|
400
|
70.00
|
5-6
|
16
|
450
|
-------
|
0.00
|