The following estimates have been prepared for a project:
Fixed costs: $5,400
Depreciation: $3,600
Sales price per unit: $3
Accounting break-even: 50,000 units
What must be the variable cost per unit? (Round your answer to 2 decimal places.)
Variable cost $_______ per unit