The following data is received from your contractor on a key component of the project: Budgeted Cost of Work Performed (BCWP) = $300 Budgeted Cost of Work Scheduled (BCWS) = $200 Actual Cost of Work Performed (ACWP) = $500 Which of the following Earned Value Management (EVM) metrics can be determined from these data?