The following 5 overhaul jobs are waiting to be processed


Problem -

The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Assume that all jobs arrived on day 180; today's date is 200.

Job

Due Date

Remaining Time (Days)

103

214

10

205

223

7

309

217

11

412

219

5

517

217

15

 Using the critical ratio scheduling rule, in what sequence would the jobs be processed?