The firm also estimates the project will require an


A firm estimates a project will cost 57000 in additional current assets nad 32000 in current liabilites. The firm also estimates the project will require an additional 7000 a year in current assets for each one of the four years of the project. How much net working capital will the firm recapture?

-85000 25000 53000 28000 85000

 