A bakery has a design capacity to bake 200 loaves of bread a day. However, due to scheduled maintenance of their equipment, management feels that they can bake 100 loaves a day. Yesterday the gas was turned off while the city was repairing a leak and only 22 loaves where baked. What was the efficiency of the ovens yesterday?