The design of a concrete mix requires 1173kg/m3 of gravel in SSD condition, 582 kg/m3 of sand in SSD condition, and 157kg/m3 of free water. The gravel available at the job site has a moisture content of 0.8% and absorption of 1.5%, and the available sand has a moisture content of 1.1% and absorption of 1.3%. What are the masses of gravel, sand, and water per cubic meter that should be used at the job site?