The Denver Iron & Steel Company is expanding its operations to include a new drive-in weigh station. The weigh station will be a heated/air-conditioned building with a large floor and small office. The large room will have the scales, a 15-foot counter, and several display cases for its equipment.
Before erection of the building, the project manager evaluated the project using AON analysis. The activities with their corresponding times were recorded in Table A.
Using AON analysis, find the critical path, the slack times, and the expected completion time.