The cycle time of the line is 5 minutes and the sum of all


You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. What is the resulting line's efficiency?