The critical path in a project network represents the:
A) Shortest duration path through the network
B) Longest duration path through the network
C) Most important tasks on a project
D) Network path using the most resources
E) Highest-risk tasks on a project
Activities which can take place at the same time are termed:
A) Parallel activity
B) Critical path
C) Burst activity
D) Merge activity
E) Independent activity
The forward pass in project network calculations determines the:
A) Earliest time's activities can begin
B) Earliest time's activities can be finished
C) Duration of the project
D) Both A and B are correct
E) A, B, and C are all correct
The backward pass in project network calculations determines the:
A) Latest time's activities can begin
B) Earliest time's activities can be finished
C) Critical path
D) Both A and C are correct
E) A, B, and C are all correct
The amount of time an activity can be delayed and yet not delay the project is termed:
A) Total slack
B) Free slack
C) Critical float
D) Float pad
E) Slip pad