The CPM (Critical Path Method) is a method to identify the critical path, which:
A-consists of all the activities in which the Project Manager is involved.
B-is composed of all non-dummy activities in the project.
C-is made of the shortest path connecting the beginning to the end of the project.
D-is made of the longest path connecting the beginning to the end of the project.