The costs cannot be reliably estimated how much revenue


1. Livesey Company has signed a long-term contract to build a new basketball arena. The total revenue related to the contract is $120 million. Estimated costs for building the arena are $40 million in the first year and $30 million in both the second and third year. The costs cannot be reliably estimated. How much revenue should Livesey Company report in the first year under iGAAP? 

Solution Preview :

Prepared by a verified Expert
Accounting Basics: The costs cannot be reliably estimated how much revenue
Reference No:- TGS01497227

Now Priced at $10 (50% Discount)