A total of 1,300 units were completed and transferred to the next processing dept during the period.Equivalent units of production in ending work in process Materials = 300 Conversion = 100Cost per equivalent unit Materials = $31.56 Conversion = $9.32Problem: Compute the cost of the units transferred to the next department during the period and the cost of ending work in process inventory?