The cost associated with lost productivity from the


A crew of mechanics at the Highway Department garage repair vehicles that break down at an average of ? = 8 vehicles per day (approximately Poisson in nature). The mechanic crew can service an average of µ= 11 vehicles per day with a repair time distribution that approximates an exponential distribution. The crew cost is approximately $300 per day. The cost associated with lost productivity from the breakdown is estimated at $150 per vehicle per day (or any fraction thereof). What is the expected cost of this system?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The cost associated with lost productivity from the
Reference No:- TGS0592918

Expected delivery within 24 Hours