The computer workstation furniture manufacturing that Santana Rey started January is progressing well. As of the end of June, Business Solutions' job cost sheets show the following total costs accumulated on three furniture jobs.
Job 6.02 was started in production in May, and these costs were assigned to it in May: direct materials, $600; direct labor, $180; and overhead, $90. Job 6.03 and 6.04 were started in June. Overhead costs is applied with a predetermined rate based on direct labor costs. Jobs 6.02 and 6.03 are finished in June, and Job 6.04 is expected to be finished in July. No raw materials are used indirectly in June. (Assume this company's predetermined overhead rate did not change over three months).
Questions:
1. What is the cost of the raw materials used in June for each of the three jobs and in total?
2. How much total direct labor cost is incurred in June?
3. What predetermined overhead rate is used in June?
4. How much cost is transferred to finished goods inventory in June?