Question: The component designer for a major off the road vehicle manufacturer estimates that she can
(a) increase the average time between failures of a part by 5%, or
(b) reduce the average repair time by 10%. Currently, the average time between failures is 100 hours and the average repair time is 4 hours.
Which option would be result in higher Availability? Show all calculations.