Average demand = 250/week
Lead time = 3 weeks
Order cost = $75/order
Unit cost = $21.50
Carrying charge rate = 0.20
Number of weeks per year = 52
The company would like to use a fixed order quantity system. What is the economic order quantity? What should be the reorder point be?