Question - Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy:
Direct materials: 6 microns per toy at $0.50 per micron Direct labor: 1.3 hours per toy at $8 per hour
During July, the company produced 3,000 Maze toys. Production data for the month on the toy follow:
Direct materials: 25,000 microns were purchased at a cost of $0.48 per micron. 5,000 of these microns were still in inventory at the end of the month.Direct labor: 4,000 direct labor-hours were worked at a cost of $36,000.
Required:
1. Compute the following variances for July:
a. The materials price and quantity variances.
material price variances: 500F
material quantity variance: 1,000U
b. The labor rate and efficiency variances.
labor rate variance: ?
labor efficiency variance: ?