Question - The budgeted hours for a factory is 11700 while its estimated total overhead is $49800. The predetermined overhead rate is calculated based on the direct labour hours. The direct materials and the direct labour used to produce a box is respectively $2.6 and $3.5 and the direct labour used is 3 mins per box.
What's the total cost of producing a single box?