XZY company employs a process costing system for its manufacturing operations. All direct materials are added at the beginning of the process and conversion costs are added propporionately. The schdule for April is listed below:
WIP on April 1 (60% complete as to conversion costs) 1000 units
Units started during april 5000 units
Total to account for 6000 units
Units completed and transferred out 4000 units
WIP on April 30 (20% complete as to conversion costs 2000 units
total units accounted for 6000 units
Costs pertaining to the month are as follows:
beginning inventory (DM, $54,000; conversion, $35,560) total $90,160
costs incurred during April (MD, $468,000, Conversion $574,060) total 1,042,060
using the weighted average method:
The equivalent units for direct materials for April are?
The equivalent units for conversion costs for April are?
The equivalent unit material cost for Arpril is?
The 4000 units completed during April will be transferred out at an EUP unit cost of what?