Activity a m b
AB 3 6 9
AC 1 4 7
CB 0 3 6
CD 3 3 3
CE 2 2 8
BD 0 0 6
BE 2 5 8
DF 4 4 10
DE 1 1 1
EF 1 4 7
Find:
(a) the AOA network and the path with the longest expected duration
(b) all event slacks
(c) critical path to event D
(d) the probability of completing the path with the longest expected duration in 14 days?
(e) the effect if DC slips to 6 days; 7 days; to 8 days