The amount of direct-labor


Greene Company uses a plantwide overhead rate with direct-labor hours as the allocation base. Use the following information to solve for the amount of direct-labor hours estimated per unit of product G2.

  • direct material cost per unit of G2 $7
  • total estimated manufacturing overhead $795,000
  • total cost per unit of G2 $20
  • total estimated direct-labor hours 530,000
  • direct labor cost per unit of G2 $3.70

1.5 DLH per unit of G2.
6.2 DLH per unit of G2.
9.3 DLH per unit of G2.
.66 DLH per unit of G2.
14.09 DLH per unit of G2.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: The amount of direct-labor
Reference No:- TGS0679824

Expected delivery within 24 Hours