The amount of activity driver used for each of burr


Burr Company has identified seven activities as part of its manufacturing process and chosen corresponding activity drivers for each activity. The chart below lists the total cost of each activity, the amount of activity driver used for each of Burr's two products, the activity rate, and the activity cost assigned to each product.

Fill in the blanks below (Omit the "$" sign in your response):




Driver Usage








Activity Cost Activity
Driver
Prod. 1 Prod. 2 Activity
Rate
Activity Cost:
Prod. 1
Activity Cost:
Prod. 2
   Design $ 53,520   Design time 960
1,270
$
/hour $    $   
   Preparation $ 31,050   Labor hours 3,030


$
/hour $ 15,150 $   
   Machining $ 137,430   Machine hours



$ 27.00 /hour $ 42,120 $   
   Finishing $
  Batches 205
320
$ 42 /batch $    $   
   Inspection $
  Units



$ 16 /unit $ 10,400 $ 19,040
   Packaging $
  Orders

51
$ 302 /order $ 11,778 $   
   Shipping $ 14,410   Packages 87


$
/package $    $ 4,840