The activities described by the following table are given for the Howard Corporation in Kansas:
ACTIVITY
|
IMMEDIATE PREDECESSOR(S)
|
TIME
|
A
|
-
|
9
|
B
|
A
|
7
|
C
|
A
|
3
|
D
|
B
|
6
|
E
|
B
|
9
|
F
|
C
|
4
|
G
|
E, F
|
6
|
H
|
D
|
5
|
I
|
G, H
|
3
|
a) Draw the appropriate AON PERT diagram for J.C. Howard's management team.
b) Find the critical path.
c) What is the project completion time?