The activities described by the following table are given


The activities described by the following table are given for the Howard Corporation in Kansas:

ACTIVITY

IMMEDIATE PREDECESSOR(S)

TIME

A

-

9

B

A

7

C

A

3

D

B

6

E

B

9

F

C

4

G

E, F

6

H

D

5

I

G, H

3

a) Draw the appropriate AON PERT diagram for J.C. Howard's management team.

b) Find the critical path.

c) What is the project completion time?